The Transmission Company of Nigeria (TCN) has appealed to the Federal Government to intervene in delays affecting the completion of the 624MW Abuja Feeding Scheme Project, a critical power infrastructure aimed at improving electricity supply to the Federal Capital Territory (FCT).
Right of Way Issues Stall Progress
TCN disclosed that the major setback to the project is Right of Way (RoW) disputes, allegedly caused by influential individuals who are resisting the passage of transmission lines through their properties.
Speaking during an inspection tour of the project, TCN’s Executive Director, Transmission System Provider, Engr. Olugbenga Ajiboye, described the situation as unfortunate, noting that the resistance is slowing down a project meant for the collective benefit of Nigerians.
“Some people do not see this project as something useful for all of us. There are powerful individuals determined that transmission lines will not pass through their land. We are appealing to the government to help resolve this issue so we can complete the project and deliver power to Abuja,” Ajiboye said.
Project Overview
According to Punch Newspaper, the project is funded by the French Development Agency (AFD) and includes:
- Five transmission substations
- 143km of 330kV transmission lines from Lafia, Nasarawa State, to Abuja
- 81km of 132kV transmission lines within Abuja
The project commenced in April 2019 and was initially scheduled for completion in December 2022.
Near Completion, Yet Delayed
Ajiboye revealed that the project is 91% completed, with two substations already finished and ready for energisation. However, unresolved RoW challenges have prevented power supply from reaching some critical locations.
He explained that:
- The Apo–Wumba transmission station cannot be energized until supply issues at Wumba are resolved.
- Once the Wumba challenge is addressed, Kuje will also receive power.
Despite the hurdles, TCN assured Nigerians that work is ongoing round the clock to ensure the project is completed and homes in Abuja benefit from improved electricity supply.
NISO Commends 350MW NNPC Abuja IPP
Meanwhile, the Nigerian Independent System Operator (NISO) has described the ongoing 350MW NNPC Abuja Independent Power Project (IPP) as a major boost toward Nigeria’s electricity generation target of 8,500MW by the end of 2026.
The Managing Director and Chief Executive Officer of NISO, Engr. Abdul Mohammed Bello, made this known during an on-site assessment of the project.
In a statement, Bello said the IPP, once operational, will:
- Significantly improve power supply to Abuja and surrounding areas
- Enhance grid diversification
- Reduce dependence on distant power generation sources
He reaffirmed NISO’s commitment to collaborating with stakeholders—including NNPC, transmission, and distribution companies—to ensure timely completion and maximum impact on Nigeria’s power sector.




![Popular Small-Size Actress Aunty Ajara Dies After Liver Illness [VIDEO]](https://thepunchng.com/wp-content/uploads/2026/02/20241109_125042-75x75.jpg)















